Initial Road Meeting 8-12-17

August 14, 2017 by pauldenroads 12 Comments

Minutes prepared by Jean:

Click here to read Road Meeting Minutes 8-12-17

The following is the 2 page Current Road Maintenance Agreement that is currently on file.

Current Road Maint. Agreement on File Page 1

Current Road Maint. Agreement on File Page 2

 

Filed Under: Meeting Minutes, News, Uncategorized

Reader Interactions

Comments

  1. James Hait says

    August 15, 2017 at 1:02 am

    Great job puting this all together! Wr appreciate all the hard work.

    Reply
  2. Jock says

    August 16, 2017 at 4:23 pm

    WE -living on Antelope Run and Poppy- support an improvement to the roads (esp. our frontage on West A.R.) and want to kick in enough up front to accomplish this. We feel a quick process that does not nec. include major drainage culverts is acceptable, as these roads have a ‘rough character’ by nature and are generally drivable. Any improvement is great, and the idea of a ‘rural’ road of character is fine by us. Let us know what is required!

    Reply
    • pauldenroads says

      August 19, 2017 at 4:16 pm

      Thank you! We are obtaining bids now.

      Reply
      • Jock says

        August 26, 2017 at 4:03 pm

        Marty ‘R Dump Truck’ man says HOE[?] HEO[?] red is the material to use as a top layer. I have seen it used and its great! [Marty:237-0021]

        Reply
        • pauldenroads says

          August 27, 2017 at 5:13 pm

          Thanks for the info…I have forwarded this to Jean.

          Reply
    • Jean Reno says

      August 21, 2017 at 11:23 pm

      Please keep us posted on when the roadbed dries out enough to work. We’ll need to see how much rock and fill will be needed…as well as not get our equipment stuck! 🙂
      -Jean

      Reply
  3. JIm Buehring says

    August 22, 2017 at 4:41 pm

    I talked to Jose last night 8/21. He is going to put together a quote for the job including maintenance. Not sure how long that will take him but he was going to look at roads today. He said he talked to jean but had the wrong # written down.
    If I don’t hear by the end of the week I will follow up.

    Reply
  4. pauldenroads says

    August 22, 2017 at 5:06 pm

    Thanks Jim. Keep us posted.

    Reply
  5. Donna Buehring says

    August 28, 2017 at 7:11 pm

    We received the proposal from Jose Sanchez trucking.
    He was able to put the proposal in 2 sections, 1 for Mitchell ($3,000 plus materials) and 1 for Antelope Run ($1,000 plus materials)

    I am forwarding the proposal to Leslie so she can place it on the website but I am also happy to email this proposal to you….just please contact me with your email address.

    NOTES:
    1 – He was unable to give an estimate at this time for Antelope Run between Patricia and Naples because of the standing water. When things dry out more, he will give us that proposal.

    2 – Antelope Run between Jean’s house and Patricia cannot be worked on because of the curve the road has taken over the years that belong to the 80 acre parcel on the north side. Luckily that section of the road does not need any repairs.

    3 – Jose stated that maintenance would be minimal once the roads are done correctly. It will not need more than a blading/scraping qtrly or semi-annual.

    If you have any questions please feel free to contact us.

    Reply
    • Donald Speer says

      August 29, 2017 at 2:39 am

      Why do you want a trucking company to do heavy equipment road work?

      Reply
      • Donna Buehring says

        August 29, 2017 at 5:40 pm

        Because he fixed a section of Antelope Run already and is very honest and dependable. He also has the exact equipment that is needed to do the repairs correctly.

        Reply
    • pauldenroads says

      August 29, 2017 at 10:10 pm

      This bid is now posted on the website.

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Primary Sidebar

Subscribe to Updates Here!

Thank you! Please check your email inbox to confirm your subscription.

Our Current Agenda

Because of costs, Antelope Run will be split into 3 jobs:

1) Naples to top of rise

2) Top of rise to Patricia

3) Patricia to Mitchell

-Holding off on this part because of construction vehicles tearing it up

Currently Working On…

Raising $3k for Antelope, and finding out about donated materials.

Recent Posts

  • Are You Willing to be the Next PRMO President?
  • Note from Jean Reno
  • Road Meeting Minutes 11-17-18
  • Road Meeting Scheduled…Be There or Be Square!
  • Update on our Road Situation

Recent Comments

  • Jerry Reeves on Note from Jean Reno
  • Mitchell Keith Peterson Jr on Road Meeting Scheduled…Be There or Be Square!
  • Lowell Speakerworth on Road Meeting Scheduled…Be There or Be Square!
  • Jean Reno on Update on our Road Situation
  • Mitchell Peterson on Update on our Road Situation

Copyright © 2023 · Metro Pro on Genesis Framework · WordPress · Log in